The CRA calendar: what applies already, and what applies from 11 December 2027.
Some of these dates are in the regulation. Some are proposed and have already moved once. Some have passed. The page says which is which.
Status as of 2 October 2026
CRA application dates
10 December 2024
In the regulationEntry into force
Regulation (EU) 2024/2847 enters into force.
11 June 2026
In the regulationNotified bodies
Chapter IV applies: conformity assessment bodies can be notified.
11 September 2026
In the regulationReporting duties in force
Reportable since this date, for products already on the market.
Today
31 October 2026
ProposedHorizontal core standards due
The principles and risk-process standard and the vulnerability-handling standard, under the Commission's draft amendment to the standardisation request.
Originally 30 August 2026
31 December 2026
ProposedVertical standards due
Product-category standards for Annex III products.
Originally 30 October 2026
2027
ExpectedFirst citations in the Official Journal
Presumption of conformity becomes available where a cited standard is applied in full.
30 October 2027
In the regulationRemaining horizontal standards due
Technical measures, including the generic security controls. Date from the standardisation request.
11 December 2027
In the regulationFull application
Annex I essential requirements, technical documentation, conformity assessment and CE marking apply in full.
After full application
OngoingThe support period
At least five years, or the expected time in use if that is shorter. Vulnerabilities must be handled for all of it.
What matters now
Decide which products are in scope, and in which class
Default, important class I or II, or critical. The class decides the conformity route and who has to be involved.
Atrekos: partlyAtrekos suggests a class from the target of evaluation you describe. The decision stays yours.
Do the risk assessment now, against the regulation text
Do not wait for the harmonised standards. An assessment done against Annex I today is what the standards will be measured against.
Atrekos: yesThis is the product.
Build the technical documentation around it
Annex VII puts the risk assessment inside the file, next to the architecture, the vulnerability-handling procedures and the support-period reasoning.
Atrekos: partlyAtrekos produces the assessment and its projections, not the whole file.
Stand up vulnerability handling and the reporting path
Article 14 applies now. Annex I Part II binds from 11 December 2027, and the 24-hour clock starts when you become aware, not when you are ready.
Atrekos: partlyAtrekos tracks Annex I Part II status; reporting and SBOM are outside it.
Plan the support period and how the assessment stays current
Decide now how a change is re-assessed, and who does it.
Atrekos: yesRe-run, diff, clone.
If the product is class II or critical, talk to a notified body early
Third-party conformity assessment takes time and the bodies are only being notified since June 2026.
Atrekos: yesThe third-party module is built for that conversation.